Build and check the schedule

The schedule is built from the bill of quantities and the health and safety plan: each activity is tied to rows of the bill, and its duration comes from the norms. Here you add an activity of your own, link it, check the schedule, and send it to the contractor in the format they work in.

  1. Open the schedule

    In the project, open Schedule. The activities are listed on the left, and the bar chart on the right has a bar for each. A red mark before the code shows the critical path: the activities whose delay moves the end of the build. Above the chart, change the scale, for example to Month; Critical only keeps only the critical activities.

    The schedule of Sunrise House: the activities on the left and their bars by month on the right.
  2. Add an activity

    Press + Activity under the list. The new row takes the next free code. Type its name, for example "Solar panels on the roof", and in the Days column the working days, for example 3. Each field is saved as you leave it. A duration typed by hand is locked, and the norms no longer recalculate it.

  3. Link it to the roof

    The panels go up after the roof. Drag the circle at the end of the "Roof and insulation" bar onto the new activity's bar. With the keyboard: select the roof's row and press L, then select the new row and press L again. The new link is finish-to-start (FS). Click its arrow to change the Link type (FS, SS, FF or SF) or to set a Lag / lead (working days), for example 2 days to clear the roof.

    An arrow from the roof's bar to the new activity, and the link's window with its type and lag.
  4. Check the schedule

    Under the title, press the badge with the schedule's rating. It opens Schedule checks: 23 checks of logic, dates, resources, performance and acts. A check without what it needs (a baseline, a target date) is left out of the count. The new activity has nothing after it, so the Logic links check names it. Press Add a link, choose "Completion of the building (Act form 15)" as the next activity, and press Add. The notes that keep the schedule from being activated are at the top.

    The schedule checks: the rating, how many checks pass, and the note about an activity with nothing after it.
  5. Send the schedule

    In the More actions menu, choose the format: MS Project (.xml) for MS Project, Export P6 (.xer) or Export P6 (PMXML) for Primavera P6, Bar chart (.xlsx) for a spreadsheet, or Print / PDF (bar chart) for paper. The MS Project and P6 files carry the activities, their durations and links, so the contractor carries on in their own program.

  6. Bring the changes back

    When the contractor returns the schedule changed in MS Project or P6, choose Import from MS Project or P6 in the same menu and pick the file. It takes XML from MS Project and XER or PMXML from P6. Before anything is saved, the preview shows each activity as new, Changed or Unchanged, and for a change both the old and the new value; the changes come first. If all is right, apply the import. A file that changes nothing has nothing to apply, and the preview says so.

    The import preview: one changed activity, with its old and new duration.
  7. The schedule on a phone

    On a phone the schedule opens as Coming up: the activities of the next 2 weeks or 6 weeks. Full programme lists every activity. Activities and links are edited on a computer, or on a tablet held sideways; sending and bringing back the files works on a phone too.

    The schedule on a phone: the activities coming up in the next two weeks, with their dates and progress.