Inspect the work, and settle non-conformances

The construction supervisor checks the works at the points agreed with the owner. Points advise: none of them stops a progress report.

  1. Read an activity's points

    On the schedule, an activity's Links and value lists its Inspection points: a Hold point the work waits for, a Witness point you are called to, each with its state, when it is due and who checks it.

    The reinforcement's inspection points
  2. Add a measured point

    Add takes what is checked, its kind, when and by whom. With Evidence set to measurement, give the required value, its tolerance and the unit, then Save.

    A measured point with its value and tolerance
  3. Check it

    Type what you measured: the point says whether it is within the tolerance. Add a note or a photo, then Passed or Failed; the check is kept with your name and the date.

    The measured value within the tolerance
  4. Fail a point

    Note what is wrong, then Failed: the point stays open and a non-conformance opens against it, major for a hold point, minor for the others. The builder sees it with the point. On a point without one, Non-conformance opens it by hand.

    The failed point with its open non-conformance
  5. Accept the fix

    The builder marks the non-conformance Fixed; once you have seen the work, Accept closes it. A closed one can be opened again.

    The accepted non-conformance
  6. Read the site layout

    On the site plan in Drawings, Site layout (health and safety plan, ПБЗ) shows the cranes' and hoists' radii, the walkways and the laydown areas. Pick a date in As of: a walkway under a hook on that date is listed in red. The household's editors draw the layout.

    The site layout with a walkway under the crane