Skip to content

All guidesBill of quantities, offers and costsSheet 4.10

Follow commitments, invoices and receipts

Costs gathers what the house is committed to, what was invoiced and paid, and what the contractor bought. Amounts are excl. recoverable VAT.

  1. Value and cost

    Costs opens on Value and cost as of the date in As of: the value to date, the cost incurred, the margin and Forecast final cost. Change the date to see an earlier month.

    Value and cost as of today, with the forecast final cost
  2. Enter an order

    In Commitments write the title and Value excl. VAT, press New commitment, then Approve. The contractor's contract is not entered here: it comes from the tender's award.

    The commitments with the new order approved
  3. Enter an invoice

    In Cost documents fill in the document's number and date, the supplier and its tax id, the amount excl. VAT and the VAT, and choose the order in Order/contract. Add document adds it as a draft.

    The invoice's details with the order chosen
  4. Approve and pay

    Approve counts the invoice into the cost. Paid today records that it was paid today.

    The invoice approved and paid
  5. Import the accountant's ledger

    Import CSV reads the purchase ledger exported as CSV. The columns are matched by their headers, or by a Saved mapping. A document already recorded is skipped, and the notice says how many.

    The notice of the import and the two documents it added
  6. Void, and lock

    An approved document is not deleted. Void asks for Reason for voiding and keeps it, marked void. Lock closes a paid document once the accountant has closed its month; it can no longer change.

    The reason typed for voiding a document entered twice
  7. The contractor's receipt

    The contractor adds a receipt from its own home: under Receipt / invoice a photo and the receipt's QR code, then Save the receipt. Add a line gives each line its Row and Material, and Save the allocation keeps them. Read the lines with AI can fill the lines in.

    A receipt with its line given to a row and a material
  8. Check the receipts

    Receipt check sets what the receipts bought against what the reported work needs: quantity × norm × (1 + waste). The note under the title gives what is normal, what needs review and what is an alert; far below the need, receipts are missing.

    The receipt check by material